General Info

The campus will consist of three acres and have three buildings, a fenced playground, and parking lot.

timeline

Timeline

Construction on Phase 2 will begin in Summer 2026.

bar_chart

Total Project Cost

$5 million

payments

Donations

Donations to this project will go toward completing the vision for a school-owned K-8 charter school campus with a community concert and lecture hall.


Progress Updates

task_alt

8-30-24, Fernwaters has completed Phase 1 of a two-phase project. We have completed the construction of the K-3 building on the northern end of the 3-acre lot. This project was funded entirely through donations, remaining ESSER funds, and capital reserves. All of the water, sewer, and electrical infrastructure is in place for Phase 2 of the project.

7-9-25 A USDA Rural Development Loan in the amount of $3.5 million was awarded. Fernwaters will construct classrooms, offices, and community performance space, Phase 2, of the Permanent Facility Project.

9-18-25. We have begun the Construction Manager Selection Process.

11-10-25. Construction Solutions Company was selected as the CM/GC on this project. Civil engineering work is in progress.

2-13-26. Contracts have been signed between Fernwaters and Resin Architecture and Fernwaters and Construction Solutions Company. Preliminary civil engineering work is complete, and construction is slated to begin in July.

3-9-26. Architectural drawings are underway. Construction is slated to begin summer 2026.